The Permian Delaware system consists of approximately 7,700 miles of natural gas gathering pipelines and 22 processing plants with an aggregate capacity of 4,007 MMcf/d, within the Delaware Basin and Central Basin in West Texas and Southeastern New Mexico, and includes aggregate gas treating capacity of 2.8 Bcf/d in addition to nine acid gas injection wells.
In response to increasing production and to meet the infrastructure needs of producers, we are constructing the Falcon II plant, the Copperhead plant, the Yeti plant and the Yeti II plant, each a 275 MMcf/d cryogenic natural gas processing plant, which are expected to begin operations in the first quarter of 2026, first quarter of 2027, third quarter of 2027 and fourth quarter of 2027, respectively.